On Thursday, November 26, Champlain Township Council unanimously voted to accept an update on plans for a full reconstruction of Vankleek Hill’s Main Street, a project being developed in partnership with the United Counties of Prescott and Russell (UCPR). Construction is not currently planned for 2027.

Deputy Director of Infrastructure Ryan Alexander presented the update to council, with the accompanying report prepared by Director of Infrastructure Marc Legault.

The proposed reconstruction covers approximately 1.8 kilometres of Main Street, which forms part of County Road 10. The project would include roadway reconstruction, sidewalks, curbs, and underground infrastructure, including watermains, sanitary sewers, and storm sewers.

The project was initiated in response to deteriorating infrastructure, with UCPR pavement assessments identifying sections of the roadway that are approximately 18 to 32 years old. The existing storm sewer system is also undersized, while the age and condition of the watermain and sanitary sewer infrastructure have raised concerns.

Alexander told council that the Township has received the consultant’s 33 per cent preliminary design submission and is reviewing it with the engineering consultant.

The project is being designed in two phases, which could be tendered separately or together. The first would cover approximately 1.15 kilometres east of Highway 34 to Terry Fox Drive, excluding the Highway 34 intersection. The second would cover approximately 650 metres west of Highway 34, including the intersection.

Proposed work also includes approximately 1,850 metres of storm sewer replacement or new construction, 1,800 metres of watermain replacement, and 1,700 metres of sanitary sewer replacement or relining. Approximately 510 metres of sanitary forcemain work are also included in the design.

The 33 per cent design was originally expected in August but was received in November. The consultant’s assignment is scheduled to be completed by Friday, December 11. Further design work, approvals, updated cost estimates, and public consultation are still required.

A previously reported initiative led by Vankleek Hill artist Susie Fairbrother and entrepreneur Samme Putzel, known as the Vankleek Hill’s Main Street Beautification Initiative, was not mentioned during the presentation. The proposal includes adding trees, shrubs, flowers, public benches, and artwork along Main Street as part of its eventual reconstruction.

The status of the initiative and whether its proposed features will be incorporated into the reconstruction project were not addressed.

The final project cost and cost-sharing arrangements between the Township and UCPR have yet to be determined.