The town Brownsburg-Chatham has announced the second phase of the renovation work already underway at the Arena Gilles-Lupien. The project mainly includes the addition of a multi-sport surface, intended to accommodate dek hockey during the summer season. Scheduled to be completed in spring 2026, these renovations will not only allow dek hockey, also basketball, futsal, as well as the organization of cultural events (exhibitions, shows, galas, etc.). This project aims to transform the arena into a true hub for leisure and sports activities, accessible not only in winter, but all year round.
The total investment, estimated at $4.8 million, of which $1.4 million comes from financial support from the federal and provincial governments. Work on the first phase was completed in October 2024 and focused mainly on the structure of the building. The $2.8 million investment included decontamination of the building, waterproofing of the foundation, drain replacement, repair of the roof and exterior cladding, modernization of the rink lighting, roof insulation and covering of the rink ceiling, addition of a sprinkler system, electrical repairs (panels and wiring) and ventilation (addition of dehumidifiers and air exchange systems in the locker rooms).
As for the second phase of the renovation work, the schedule will be divided into two separate blocks. First, the renovation work already announced will begin in spring 2025, with completion scheduled for September 2025. This includes changing the rink’s boards, modifying the stands and adding seats, reconfiguring the players’ and officials’ benches, modernizing the players’ locker rooms, redeveloping the entrance hall, renovating the washrooms and installing sponsor signage. Second, the addition of the multi-sport surface and work to transform the Arena Gilles-Lupien into a year-round recreation and sports centre will take place in spring 2026.