R. W. Tomlinson Construction is advising of ramp closures at the end of August to allow completion of paving work.

The Highway 417 eastbound on/off ramps at the Highway 34 interchange south of Vankleek Hill will be closed on the nights of August 26 and 27. There will be individuals on-site to direct traffic during the closures of the ramp. The schedule of construction will be as follows:

On August 26 at 9 p.m., the eastbound on/off ramps will be closed.

From 9 p.m. on August 26 to 6 a.m. on August 27, completion of the milling of the eastbound on/off ramps will take place, as well as the paving of the eastbound off ramp at the Highway 34 interchange.

On August 27 at 9 p.m., the eastbound on ramp will be closed. On August 27, from 9 p.m. to August 28 at 6 a.m., workers will complete the paving of the eastbound on ramp at the Highway 34 interchange.